Clean roadway of objectionable materials and perform any necessary patching or pre-milling
Crush and screen the RAP, if required
Feed RAP, recycling agent and any additives into the cold mix plant
Transfer the recycled mix to the site in haul trucks
Tack the existing surface prior to placement of the CCPR mix
The recycled mix is either placed in a windrow on the pavement and placed into a paver using a windrow elevator or placed directly into the paver hopper
The mat is compacted by heavy pneumatic and double drum vibratory rollers
A fog seal and blotter sand are applied if raveling is a concern
The road is opened to traffic soon after compaction is achieved (within hours)
The recycled mixture is allowed to cure for a minimum of three days
With emulsified asphalt recycling agent, consider rerolling when the pavement temperature exceeds 80 F (27 C) to reduce air voids.
A surface course is applied after the recycled mixture has cured
Application Guidelines
CONTROL STRIP:
If required, a control strip should be placed in conditions similar to those that are expected to occur during construction.
Recycling Agent and Additives:
Added at the central plant
Verify application rate using meter on plant
MIXTURE:
Particles should look evenly coated
Particle size should meet specification requirements (especially top size)
No blobs or stringers of undispersed recycling agent
Not segregation in windrow or in paver
FRESH MAT:
Uniform look with no major segregation, streaks or fat spots
Placed to consistent depth
The mat will look coarser than a typical hot mix mat. This is normal, as the CCPR mix has higher voids and larger aggregate max size than dense graded asphalt. With rolling traffic the surface of the CCPR mix will knead together and look tighter.
At first, the mat may look brown. Some emulsified asphalts have a brownish color before the emulsion breaks and turns black. This happens soon after placing.
Check for slope / crossfall directly behind the paver
COMPACTION:
Established rolling pattern via control strip to achieve target density
Ensure roller drums are clean and not covered with picked up material
Roller skirts are not needed as the mix temperature is close to ambient
Rollers should not be stopped on the fresh mat
For foamed asphalt mixes, keep the water content at optimum moisture content to aid compaction
Check compaction with nuclear gauge
Check slope with straightedge / smart level after final roller
RETURN TO TRAFFIC:
Control traffic to keep stopped traffic off the fresh mat
Traffic should be piloted slowly on the fresh mat to prevent ravelling
If fog seal is used to prevent raveling, apply sand blotter and/or wait for the fog seal to cure before allowing traffic
Watch for early signs of rutting, ravelling, or other distresses, and notify the contractor immediately if a problem persists
Let's Connect
Get the latest in industry trends, research, success stories, and technical updates in a succinct e-newsletter.
PPRA Industry News Signup
Thank you!
Thank you for signing up for the PPRA mailing list!
If you created an account, you should receive an email shortly with more instructions to activate your account.