Full Depth Reclamation
Find a Contractor/Supplier

Suitable Conditions


Unsuitable Conditions

• FDR should not be performed when the pavement is frozen or freezing temperatures are anticipated within 7 days of the end of FDR placement

• A minimum ambient temperature of 35 °F (2 °C) is recommended for chemical stabilizing agents

• A minimum ambient temperature of 45 °F (7 °C) is recommended for bituminous stabilizing agents

• FDR should not be performed in moderate to heavy rain