Full Depth Reclamation
- Construction
- Weather Requirements
Find a Contractor/Supplier
Suitable Conditions
Unsuitable Conditions
• FDR should not be performed when the pavement is frozen or freezing temperatures are anticipated within 7 days of the end of FDR placement
• A minimum ambient temperature of 35 °F (2 °C) is recommended for chemical stabilizing agents
• A minimum ambient temperature of 45 °F (7 °C) is recommended for bituminous stabilizing agents
• FDR should not be performed in moderate to heavy rain